Skip to main content

Worked Example: Cable Pulling Feasibility for a 185mm² Feeder at an Open-Pit Mine

Step-by-step cable pulling tension calculation for a 185mm² Cu 3C+E XLPE feeder through a 150m cable route with two 90° bends at a copper-gold mining operation. Covers pulling tension, SWBP, jam ratio, and conduit fill per NEC and IEEE 1185.

NEC / IEEE 118515 min readUpdated March 24, 2026
Share:

The Challenge: Pulling Feeders Through a Mining Process Plant

At a copper-gold mining operation, electrical engineers regularly face demanding cable installation scenarios: pulling heavy power feeders through long cable duct routes across the process plant, with tight bend radii around structural steelwork, elevation changes between levels, and limited access during shutdowns.

A typical scenario involves installing a 185mm² Cu 3C+E XLPE feeder cable from the pit-rim switchroom to supply a primary crusher motor. The cable route passes through a 150m duct run with a 25m elevation change (approximately 10° incline on the ramp section) and two mandatory 90° bends where the route changes direction around haul road crossings and plant steelwork.

Getting this wrong means a cable stuck mid-pull, a wrecked cable jacket from excessive sidewall bearing pressure, or worse — a cable that passes installation but fails in service due to conductor damage from overpulling. Each failed pull attempt costs the operation approximately A$15,000 in labour, cable, and production downtime.

This worked example demonstrates how ECalPro’s Cable Pulling Calculator models the physics of this installation and determines feasibility before the cable drum even reaches site.

Input Parameters

ParameterValueSource
Cable185mm² Cu 3C+E XLPEProject specification
Cable OD49.0 mmNexans Olex datasheet
Cable weight8.49 kg/mNexans Olex datasheet
Number of cables1
InstallationHDPE duct, 110mm IDSite specification
Friction coefficient (μ)0.30HDPE duct, dry
SWBP limit5,000 N/mIEEE 1185

Route Segments (Pull Direction A: Switchroom → Crusher)

#TypeDetail
1Straight60m at 0° (horizontal run from switchroom)
2Bend90°, r = 0.8m (first direction change at haul road crossing)
3Straight50m at 10° incline (ramp down to crusher level)
4Bend90°, r = 0.8m (second direction change around plant steelwork)
5Straight40m at 0° (level approach to crusher MCC)

Step 1: Cable Weight Force

The cable weight force per unit length is the foundation of all tension calculations:

w = m × g = 8.49 × 9.81 = 83.29 N/m — (Eq. 1)

For a single 185mm² 3C+E XLPE cable at 8.49 kg/m, the gravitational force is 83.29 newtons per metre of cable. This force drives both the friction component (horizontal) and the gravity component (inclined sections).

Step 2: Maximum Allowable Tension

The maximum pulling tension that the conductor can withstand without permanent deformation:

Tmax = k × A = 70 × 185 = 12,950 N (12.95 kN) — (Eq. 2)

For copper conductors, k = 70 N/mm² per AEIC CS8 and NEC Section 300.17. This is the absolute ceiling — exceeding this tension risks stretching the conductor, reducing its cross-sectional area, and increasing resistance permanently.

Step 3: Conduit Fill Check

Before calculating tension, verify the cable physically fits in the duct:

Fill% = (π × (49/2)²) / (π × (110/2)²) × 100 = 1,885.7 / 9,503.3 × 100 = 19.8% — (Eq. 3)

For a single cable, the NEC Chapter 9, Table 1 limit is 53%. Our fill of 19.8% is well within limits. ✓ PASS

Step 4: Segment-by-Segment Tension (Direction A)

Now we calculate the cumulative tension through each segment, starting from Tin = 0 N at the switchroom:

Segment 1: Straight 60m at 0°

T1 = 0 + 83.29 × 60 × 0.30 × cos(0°) + 83.29 × 60 × sin(0°)

T1 = 0 + 1,499.2 + 0 = 1,499 N — (Eq. 4)

Segment 2: Bend 90°, r = 0.8m

Applying the capstan equation:

T2 = T1 × e(μ × θ) = 1,499 × e(0.30 × π/2) = 1,499 × 1.602 = 2,402 N — (Eq. 5)

SWBP at this bend: 2,402 / 0.8 = 3,003 N/m (within 5,000 N/m limit)

Segment 3: Straight 50m at 10° (ramp to crusher level)

T3 = 2,402 + 83.29 × 50 × 0.30 × cos(10°) + 83.29 × 50 × sin(10°)

T3 = 2,402 + 1,232.1 + 723.1 = 4,357 N — (Eq. 6)

Note the 10° incline adds 723 N from gravity — a 16% increase over a horizontal run of the same length.

Segment 4: Bend 90°, r = 0.8m

T4 = 4,357 × e(0.30 × π/2) = 4,357 × 1.602 = 6,980 N — (Eq. 7)

SWBP at this bend: 6,980 / 0.8 = 8,725 N/m

✗ SWBP EXCEEDS 5,000 N/m LIMIT! This is the critical finding.

Segment 5: Straight 40m at 0°

T5 = 6,980 + 83.29 × 40 × 0.30 = 6,980 + 999.5 = 7,980 N — (Eq. 8)

Step 5: Results Assessment

CheckValueLimitStatus
Max Tension7,980 N (7.98 kN)12,950 N (12.95 kN)PASS (62%)
Max SWBP8,725 N/m5,000 N/mFAIL (175%)
Conduit Fill19.8%53%PASS

Verdict: FAIL — The pulling tension is acceptable, but SWBP at Bend 4 exceeds the IEEE 1185 limit by 75%. The cable jacket will likely sustain damage during installation.

Step 6: Remediation Options

The ECalPro calculator identifies the problem before the pull attempt. Here are the engineering solutions, ordered by effectiveness:

  1. Increase bend radius to 1.5m: SWBP = 6,980/1.5 = 4,653 N/m — within limit. This requires rerouting the duct with a wider sweep at the direction change, which is feasible if identified during design.
  2. Use cable lubricant: Reducing μ from 0.30 to 0.15 (lubricated HDPE) cuts tension at Bend 4 from 6,980 N to approximately 4,100 N — SWBP = 5,125 N/m. Marginal but potentially acceptable.
  3. Pull from the opposite direction: Direction B (crusher end → switchroom) encounters the steep incline as a downhill run, reducing gravity-assisted tension buildup before the critical bends.
  4. Install an intermediate pull point: Break the route into two pulls with a junction box at the midpoint, ensuring each pull segment stays within SWBP limits.

In practice, the combination of cable lubricant and pulling from the crusher end (Direction B) proved successful, with measured SWBP below 4,000 N/m throughout the route.

Try It Yourself

ECalPro’s Cable Pulling Calculator performs this entire analysis in seconds, including bidirectional comparison and segment-by-segment tension profiling. Model your actual route, cable, and conduit parameters to verify feasibility before committing to installation.

The calculator supports single-core and multi-core cables from 1.5mm² to 400mm², with reference data from Nexans, Prysmian, and Olex catalogues. Override cable OD and weight with your actual datasheet values for maximum accuracy.

Try the cable-pulling Calculator

Put this methodology into practice. Calculate results with full standard clause references — free, no sign-up required.

Or embed this calculator on your site
Calculate cable-pulling

Frequently Asked Questions

For a 185mm² copper conductor, the maximum allowable pulling tension is 70 × 185 = 12,950 N (12.95 kN) per AEIC CS8 and NEC Section 300.17. This assumes pulling via a pulling grip on the conductor. For aluminium, the limit is 40 × 185 = 7,400 N.
SWBP = T / r, where T is the tension at the bend exit (in newtons) and r is the bend radius (in metres). IEEE 1185 recommends a maximum of 5,000 N/m. Tight bends and high tension are the critical combination — always check SWBP at every bend in the route.
For dry HDPE duct, use μ = 0.30 as a starting point. With cable lubricant (soap or polymer-based), the coefficient can reduce to 0.15–0.20. For PVC conduit, use μ = 0.35 dry. Always verify with manufacturer data for specific cable/duct combinations.

Related Resources