Electrical Testing & Commissioning Checklist (PDF)

Free download · A4 (210 × 297mm) — 2 pages

Electrical testing and commissioning is required for every new installation, modification, and periodic inspection. This checklist covers the complete test sequence: visual inspection, earth continuity (R1+R2), insulation resistance (IR) at 500V DC, polarity verification, earth fault loop impedance (Zs), prospective fault current (PSCC), RCD trip time and trip current, phase sequence, and voltage measurements. Each test has fields for expected value, measured value, instrument serial number, and pass/fail status. Formatted for BS 7671 Part 6, AS/NZS 3017, and IEC 60364-6 test requirements. Includes a certificate of compliance section with engineer sign-off.

What's Included

Front:Visual inspection checklist, earth continuity (R1+R2), insulation resistance (IR), polarity, earth fault loop impedance (Zs), PSCC.
Back:RCD testing (trip time and current), phase sequence, voltage measurements, certificate of compliance, engineer sign-off.
Size:A4 (210 × 297mm) — 2 pages
Format:PDF, print-ready

How to Print

  • Open in Microsoft Excel 2016+, Google Sheets, or LibreOffice Calc
  • Add your company logo and project details to the header
  • Copy data rows to add more circuits or equipment
  • Print on A4 or A3 landscape for site records
  • Keep completed records for design verification and audit trail

Try the Interactive Calculator

Need precise calculations beyond quick reference? Try our free online calculator with full clause references and professional report output.

Open Calculator

Frequently Asked Questions

What tests are required for electrical commissioning?

At minimum: earth continuity, insulation resistance, polarity, earth fault loop impedance, RCD operation, and prospective fault current. BS 7671 Regulation 643 and AS/NZS 3017 define the full test sequence.

Which standard does this checklist follow?

The test sequence follows BS 7671:2018+A2 Part 6, AS/NZS 3017:2022, and IEC 60364-6. Adjust test acceptance criteria for your specific standard and jurisdiction.

What instruments do I need?

A calibrated multifunction installation tester (e.g., Megger MFT or Fluke 1664 FC) covers all tests. You will also need a proving unit and GS38 compliant test leads.