Skip to main content

Challenge: Size a Cable for This 132kW Motor in a 45°C Ambient Tray Installation

Work through a real-world cable sizing challenge: 132kW, 415V, 3-phase motor on perforated tray at 45 degrees C ambient with 4 other circuits. Calculate design current, apply derating factors, select cable size per IEC 60364-5-52 and AS/NZS 3008.1.1, and verify voltage drop.

IEC 603645 min readUpdated March 12, 2026
Share:

The Problem

Challenge: Size the power cable for the following motor installation. All parameters are given — work through the calculation before reading the solution.
ParameterValue
Motor rated power132 kW
Supply voltage415 V, 3-phase, 50 Hz
Motor power factor0.87
Motor efficiency0.95 (IE3)
Cable run length45 m
Installation methodPerforated cable tray — IEC Reference Method E
Ambient temperature45°C
Other circuits on tray4 (total 5 circuits including this one)
Cable insulationXLPE, copper conductors
Protection deviceMCCB, to be selected
Voltage drop limit5% (20.75 V line-to-line)

Take a moment. Calculate the design current. Identify the derating factors. Select the cable. Then read on.

Work Through It

Step 1: Calculate the design current (Ib).

The motor draws power from the supply. The supply current includes losses in the motor (efficiency) and the reactive component (power factor):

Ib = P / (√3 × V × PF × η)

Ib = 132,000 / (√3 × 415 × 0.87 × 0.95)

Ib = 132,000 / (1.732 × 415 × 0.87 × 0.95)

Ib = 132,000 / 594.0

Ib = 222.2 A

Step 2: Select the protection device rating (In).

The MCCB must be rated at or above Ib. Standard MCCB ratings: 200, 225, 250, 315, 400 A. For a motor circuit, also consider starting current — but for cable sizing, we need In ≥ Ib:

In = 250 A (next standard rating above 222.2 A)

Step 3: Determine the required tabulated current (It).

The cable must carry In after derating factors are applied:

It ≥ In / (Ca × Cg)

Where Ca is the ambient temperature correction factor and Cg is the grouping correction factor.

Ambient temperature correction (Ca):

For XLPE insulation (90°C maximum operating temperature) at 45°C ambient, from IEC 60364-5-52, Table B.52.14:

Ca = 0.87

Grouping correction (Cg):

For 5 circuits on a perforated tray (single layer, touching), from IEC 60364-5-52, Table B.52.17:

Cg = 0.73

Required tabulated current:

It ≥ 250 / (0.87 × 0.73)

It ≥ 250 / 0.635

It ≥ 393.7 A

The Solution

IEC 60364-5-52 selection:

From IEC 60364-5-52, Table B.52.10 (Reference Method E, XLPE, copper, 3-phase), find the cable with tabulated current ≥ 393.7 A:

Cable Size (mm²)Tabulated Current (A)Adequate?
120346No — 346 < 393.7
150391No — 391 < 393.7
185448Yes — 448 > 393.7

Selected cable: 185 mm² 4-core XLPE/copper

Note the 150 mm² cable at 391 A is tantalisingly close to the required 393.7 A. This is where shortcuts kill you. A 2.7 A shortfall means the cable is undersized. There is no rounding down in cable sizing.

AS/NZS 3008.1.1:2017 comparison:

Under AS/NZS 3008.1.1:2017, the reference ambient is 40°C. The ambient derating from 40°C to 45°C is less severe (Ca = 0.90 from Table 6), but the base tabulated currents in Table 13 for the same installation method may differ slightly. The grouping factors from Table 22 for 5 circuits on a perforated tray give Cg = 0.73 (same as IEC for this configuration). Working through the AS/NZS calculation typically yields the same 185 mm² result for this scenario, though the margin is more comfortable because the ambient derating is less severe.

Voltage Drop Check

Cable sized for current capacity — now verify voltage drop. For 185 mm² copper cable at 45 m:

From IEC 60364-5-52 tables or manufacturer data, the mV/A/m value for 185 mm² 4-core XLPE at 0.87 PF is approximately 0.23 mV/A/m (combining resistive and reactive components).

Vd = (mV/A/m × Ib × L) / 1000

Vd = (0.23 × 222.2 × 45) / 1000

Vd = 2.30 V

As a percentage of supply voltage:

Vd% = (2.30 / 415) × 100 = 0.55%

This is well within the 5% limit (20.75 V). Voltage drop is not the governing factor for this installation — the cable size is determined by current capacity after derating.

If the run were longer — say 200 m (common in mining and industrial plants) — voltage drop would become the controlling factor and might push the cable to 240 mm² or beyond, regardless of current capacity.

Key Learning

What made this challenge tricky:

  • The combined derating factor is severe. Ca × Cg = 0.635. The cable must carry 57% more current than the protection device rating to account for the hot, crowded installation environment. Engineers who forget either factor — or who apply them to Ib instead of In — will undersize the cable.
  • The 150 mm² trap. At 391 A versus 393.7 A required, the 150 mm² cable looks adequate at first glance. It is not. A cable that is 99.3% of the required rating is still undersized. In a real installation, this 2.7 A margin could be consumed by any deviation from assumed conditions.
  • Motor efficiency matters. Omitting the 0.95 efficiency factor would give Ib = 211 A instead of 222 A. That 11 A difference would not change the cable size in this case, but in a borderline scenario it is the difference between a cable that passes and one that does not.
  • Power factor in the design current. PF = 0.87 means the motor draws more current per kilowatt of mechanical output than a unity PF load. Forgetting PF in the Ib calculation is the most common motor cable sizing error — it undersizes the cable by approximately 15%.

Try the Cable Sizing Calculator

Put this methodology into practice. Calculate results with full standard clause references — free, no sign-up required.

Or embed this calculator on your site
Calculate Cable Sizing

Frequently Asked Questions

Use the nameplate full-load current (FLC) if available, as it includes the actual efficiency and power factor of the specific motor. The calculated value using rated power, voltage, PF, and efficiency is an estimate used when the nameplate data is not yet available (during design stage before motor procurement). Once the motor is selected, verify the cable sizing against the actual nameplate FLC.
Motor starting current (typically 6-8 times FLC for DOL start) does not normally affect cable sizing because the duration is short (typically 5-15 seconds). However, it affects protection device selection — the MCCB must not trip during starting. For cable sizing, use the continuous running current. For frequent-start motors (more than 10 starts per hour), the thermal effect of starting current on the cable should be checked.
If physical space is the constraint, consider running the motor circuit on a separate tray or in a dedicated trefoil arrangement on the same tray with spacing from other circuits. Separating this circuit eliminates the grouping factor (Cg = 1.0), which reduces the required tabulated current to 287A and allows a 120mm2 cable. The additional tray cost is often less than the cable cost difference between 120mm2 and 185mm2 over a 45m run.

Related Resources