Challenge: Size the Transformer for This Hospital — It's Not Just kVA
A 2,000 kVA load study for a hospital. But harmonics, motor starting, and essential services change everything. What size transformer do you actually need?
February 26, 2026
The Problem
A new 200-bed regional hospital. The maximum demand study shows:
| Load Category | Demand (kVA) |
|---|---|
| Lighting (LED throughout) | 280 |
| General power (GPOs, IT) | 420 |
| HVAC (chillers, AHUs, fans) | 650 |
| Medical equipment (imaging, theatres) | 310 |
| Kitchen and laundry | 180 |
| Lifts and vertical transport | 120 |
| Total calculated demand | 1,960 kVA |
The project electrical engineer specifies a 2,000 kVA transformer with 5% impedance. Is this correct?
The Challenge
Identify at least four reasons why a 2,000 kVA transformer is wrong for this application, and determine the correct size.
The Solution
Problem 1: Harmonic Derating
LED lighting (280 kVA) and IT/GPO loads (420 kVA) are high-harmonic sources. Combined, they represent 700 kVA of non-linear load — 36% of total.
Per IEEE C57.110, a transformer supplying significant harmonic loads must be derated. With a K-factor of approximately 7 (typical for mixed LED/IT load profile), the transformer must be derated to approximately 85% of nameplate capacity.
2,000 kVA × 0.85 = 1,700 kVA effective capacity — insufficient for 1,960 kVA demand.
Problem 2: Motor Starting Voltage Dip
The largest HVAC chiller has a 200 kW DOL-start compressor motor. Starting current: approximately 6× FLC = ~1,800A at 415V = ~1,300 kVA.
Voltage dip during motor starting:
ΔV% = (S_start / S_tx) × Z_tx% = (1,300 / 2,000) × 5% = 3.25%
AS/NZS 61000.3.3 and most hospital standards require voltage dips to be less than 3% for sensitive medical equipment. At 3.25%, imaging equipment (MRI, CT) may produce artefacts or require recalibration.
Increasing transformer size to 2,500 kVA: ΔV% = (1,300 / 2,500) × 5% = 2.6% — passes.
Problem 3: Essential Services Redundancy
Hospital electrical systems require redundancy per AS/NZS 3009 (Electrical installations — Emergency power supplies in hospitals). Essential services (theatres, ICU, emergency department) must have:
- N+1 transformer configuration or automatic changeover from utility to generator
- If using a single transformer, it must be rated for the essential load with adequate margin for generator synchronisation transients
Essential services typically represent 60–70% of hospital demand. If the single transformer fails, the generator must support ~1,300 kVA. The transformer itself needs headroom above calculated demand for transient load acceptance.
Problem 4: Future Load Growth
Hospital load typically grows 2–3% per year as services expand and technology evolves. Over a 20-year transformer life:
1,960 kVA × (1.025)^20 = 3,211 kVA
Even with conservative 1.5% growth: 1,960 × (1.015)^20 = 2,638 kVA
The Correct Specification
| Consideration | Required Capacity |
|---|---|
| Calculated demand | 1,960 kVA |
| Harmonic derating (K-7, 85%) | 2,306 kVA minimum nameplate |
| Motor starting (ΔV < 3%) | 2,500 kVA minimum |
| 10-year growth (1.5%/yr) | 2,271 kVA demand |
| 20-year growth (1.5%/yr) | 2,638 kVA demand |
Recommended: 2,500 kVA transformer (or 2×1,600 kVA in parallel for redundancy), with K-factor rating or de-rated accordingly.
The 2,000 kVA specification was undersized by 25% once real-world factors were considered.
Run your own analysis: Use the Transformer Calculator and Maximum Demand Calculator together.
Frequently Asked Questions
How do I size a transformer?
Size based on maximum demand (not connected load), diversity factors per AS/NZS 3000 Table C2, and future growth (typically 125-150% of current load). Don't forget power factor correction and harmonics per IEEE C57.110.
Related Articles
- Transformer Calculator - Interactive calculator with standards compliance
- Max Demand - Interactive calculator with standards compliance
- Harmonics Analysis - Interactive calculator with standards compliance
Try It Yourself
Run the calculations from this article using our free calculators: