Maximum Demand Calculation — Diversity Factors Explained Step-by-Step
Calculate maximum demand with diversity factors in 3 steps. Covers AS/NZS 3000, IEC 60364 & NEC Article 220 methods. Free calculator included.
A young engineer once presented me with a transformer sizing calculation for a 200-unit apartment complex. Each unit had a 63A main breaker at 230V — a connected load of 14.5 kW per unit. His conclusion: the building needed a 200 × 14.5 = 2,900 kVA supply, requiring two 1,500 kVA transformers.
The actual maximum demand of that building, measured over 12 months after occupation, peaked at 680 kVA. He had over-estimated by 4.3× — recommending $180,000 worth of transformer capacity that would never be used.
The missing concept was diversity — the statistical certainty that not all loads operate simultaneously at their maximum rating.
Connected Load vs Maximum Demand
Connected load is the sum of all individual load ratings. It's the theoretical maximum if every appliance, light, and socket outlet in a building operated at full capacity simultaneously. This never happens.
Maximum demand (or After Diversity Maximum Demand — ADMD) is the highest actual load that the installation draws from the supply over a representative period. It accounts for the fact that:
- Not all circuits operate simultaneously
- Most loads operate below their rated capacity
- Load peaks from different circuits occur at different times
- Some loads are intermittent (motors, lifts, HVAC compressors cycle on and off)
Diversity Factor
Maximum Demand = Connected Load × Diversity Factor
Diversity factors are always less than 1.0 (often much less). The more loads in a system, the lower the diversity factor — because the probability of ALL loads operating simultaneously decreases with the number of loads.
How Diversity Factors Work
Consider a simple example: 10 identical apartments, each with a 10 kW connected load.
- The connected load is 100 kW
- Each apartment's peak demand occurs at different times (one is cooking while another is idle; one is running air conditioning while another is switched off)
- The measured maximum demand might be 45 kW — a diversity factor of 0.45
Now consider 100 identical apartments:
- Connected load: 1,000 kW
- Maximum demand: approximately 300 kW — diversity factor of 0.30
And 500 apartments:
- Connected load: 5,000 kW
- Maximum demand: approximately 1,200 kW — diversity factor of 0.24
The Law of Large Numbers
Diversity improves with scale. A single apartment might use 0% or 100% of its connected load at any moment. But 500 apartments together form a statistical population — the probability that ALL are at peak simultaneously is astronomically small. This is why supply authorities can serve millions of customers without providing generating capacity equal to the total connected load.
Standard Methods
AS/NZS 3000 (Wiring Rules)
AS/NZS 3000, Section 2, Part C — Maximum demand assessmentAS/NZS 3000 provides specific tables for calculating maximum demand by load category. The method:
- List all loads by category (lighting, socket outlets, cooking, heating, air conditioning, motors)
- Apply the specific demand factor for each category:
- Lighting: first 2 kVA at 100%, remainder at 50%
- Socket outlets: first 20 at 10A each (100%), next 20 at 5A each, remainder at 2.5A each
- Cooking: first appliance at 100%, each additional at a reducing percentage
- Sum the diversified loads to get the maximum demand
- Apply an overall diversity factor for the number of consumers (for multi-unit installations)
The diversity factors for multiple residential units in AS/NZS 3000:
| Number of Units | Diversity Factor (per unit ADMD) |
|---|---|
| 1 | 1.00 |
| 5 | 0.75 |
| 10 | 0.62 |
| 20 | 0.52 |
| 50 | 0.44 |
| 100 | 0.38 |
| 200 | 0.33 |
| 500 | 0.28 |
BS 7671 (IET Wiring Regulations)
BS 7671, Appendix A, Table A1 — Current demand of points of utilisationBS 7671 Appendix A provides guidance on assessing current demand. The approach is similar but expressed differently:
- Socket outlets: first point at rated current, additional points at 40% or less depending on usage
- Lighting: 66 VA per point (standard), or rated value for discharge lighting
- Cooking: 10A + 30% of remainder above 10A + 5A per additional appliance
- Space heating: full rated current (no diversity for heating — it all runs when it's cold)
- Motors: full-load current of largest motor + 40% of remaining motors
No Diversity for Heating
Both BS 7671 and IEC standards apply zero diversity to space heating loads. On the coldest day of the year, every heater runs continuously. An engineer who applies diversity to heating loads will undersize the supply — and the building will be cold when the occupants need heat most.
IEC 60364
IEC 60364-8-1, Clause 8.1 — Energy efficiency — assessment of demandIEC 60364 takes a more general approach, requiring the designer to assess maximum demand based on "knowledge of the intended use of the installation." It references load profiles and diversity factors but doesn't provide specific tables — instead, national committees (who adopt IEC 60364 into their national standards) provide the detailed factors.
The Common Mistakes
Mistake 1: Adding Up Circuit Breaker Ratings
The most egregious error. A 20A MCB on a lighting circuit doesn't mean that circuit draws 20A. A typical residential lighting circuit draws 2–3A. The MCB is sized for protection, not to indicate the actual load.
Adding up all MCB ratings in a distribution board gives the breaking capacity sum, not the maximum demand. For a typical residential DB with a 63A main breaker and twenty 20A MCBs, the sum of MCB ratings is 400A — but the maximum demand is the 63A main breaker rating (which itself includes diversity).
Mistake 2: Applying Diversity to the Wrong Level
Diversity factors apply at each level of the distribution hierarchy, but you can't apply them cumulatively without understanding the basis.
Correct approach: Calculate the maximum demand at each distribution board using the appropriate diversity factors for the loads it serves. Then apply inter-board diversity to get the main switchboard demand.
Incorrect approach: Calculate the undiversified load at each board, sum them all, and apply a single blanket diversity factor. This ignores the different diversity characteristics of different load types.
Mistake 3: Using Generic Diversity Factors for Specialised Buildings
The diversity factors in standards are based on typical residential or commercial usage patterns. They don't apply to:
- Data centres: virtually 100% diversity factor (all equipment runs continuously)
- Industrial process plants: diversity depends entirely on the process — a batch plant has high diversity, a continuous process has low diversity
- Hospitals: lighting and HVAC have normal diversity, but medical equipment and critical services have near-zero diversity
- Mining operations: process plant diversity is typically 0.7–0.85 (much higher than commercial buildings because the equipment runs continuously during operation)
Data Centres Have No Diversity
A data centre with 1,000 kW of server load and 400 kW of cooling has a maximum demand of approximately 1,400 kW — diversity factor close to 1.0. Applying a commercial building diversity factor of 0.5 would undersize the supply by 50%, causing immediate problems.
Mistake 4: Ignoring Future Growth
A maximum demand calculation is a snapshot. If the building is likely to add loads in future (EV charging, additional air conditioning, kitchen upgrades in apartments), the transformer and main cable should be sized with margin.
Good practice: add 20–30% growth allowance for commercial buildings, and specifically account for EV charging infrastructure in residential developments. Many jurisdictions now require EV-ready provisions for all new residential units.
The Cost of Getting It Wrong
Oversized Supply (Most Common)
- Transformer operates at 20–30% of capacity — poor power factor, higher losses, higher capital cost
- Switchboard rated for unnecessary fault level (larger transformer = higher fault current)
- Main cables oversized — wasted copper, larger cable routes, higher installation cost
- Typical cost penalty: 30–50% more than a correctly sized installation
Undersized Supply (Dangerous)
- Transformer overloads during peak periods — accelerated insulation ageing, potential failure
- Voltage drops below acceptable limits — equipment malfunctions, motor stalling
- Protection devices trip under normal load — service interruptions
- Main cables overheat — fire risk
- Typical resolution: emergency transformer upgrade ($50,000–200,000 depending on size), disruption to occupants
Worked Example: Small Commercial Building
Building: 3-storey office building, 2,000m² total
| Load Category | Connected Load (kW) | Demand Factor | Maximum Demand (kW) |
|---|---|---|---|
| Lighting (LED) | 40 | 0.90 | 36 |
| Socket outlets (200 double) | 96 | 0.30 | 29 |
| Air conditioning | 120 | 0.85 | 102 |
| Lifts (2 × 15 kW) | 30 | 0.60 | 18 |
| Server room | 15 | 1.00 | 15 |
| Kitchen/tea points | 24 | 0.40 | 10 |
| Total | 325 | 210 |
Overall diversity factor: 210/325 = 0.65
For transformer sizing (accounting for power factor of 0.85):
Transformer Sizing
S = P_max / PF = 210 / 0.85 = 247 kVA → select 315 kVA transformer
Without diversity analysis, the engineer would calculate 325/0.85 = 382 kVA → select 500 kVA. The 500 kVA transformer costs approximately $8,000–12,000 more than the 315 kVA, has higher no-load losses (running costs), and delivers higher fault current to the switchboard (potentially requiring a higher-rated board).
The Mining Context
At a large-scale mining operation, maximum demand for the processing plant was calculated using actual motor duty cycles from the process design. The SAG mill (6 MW), ball mills, flotation cells, thickeners, and pumps have well-defined operating profiles. The overall plant diversity factor was 0.78 — meaning the 45 MW connected load had a maximum demand of approximately 35 MW.
But during plant startup — when all conveyors, mills, and pumps start in sequence — the demand transiently exceeds the steady-state maximum by 40% due to motor starting currents. The power supply and emergency generation had to be sized for this starting sequence, not just the steady-state demand.
This illustrates a key point: maximum demand must consider both steady-state and transient conditions.
Practical Recommendations
- Always perform a formal maximum demand assessment — never use the sum of MCB ratings or connected load as the design basis
- Use the appropriate standard method for your jurisdiction (AS/NZS 3000 tables, BS 7671 Appendix A, or local national annex to IEC 60364)
- Apply different diversity factors for different load types — don't use a blanket factor
- Never apply diversity to heating or data centre loads — these run at or near full capacity when they're needed
- Allow for future growth — 20–30% for commercial, specific provision for EV charging in residential
- Validate against real data where possible — metered data from similar buildings is the best design basis
Related Resources
- Auckland CBD Crisis: Maximum Demand Calculation — How underestimated demand caused a city-wide power failure
- Maximum Demand: The 20-Unit Apartment Block — 14% gap in demand between standards
- Cable Sizing: The 50m Office Feeder — Cable sizing flows directly from demand calculation
- View all worked examples →
Try the Maximum Demand Calculator
Free online tool — no signup required
Try the Maximum Demand Calculator
Free online tool — no signup required
Try the Transformer Calculator
Free online tool — no signup required
Frequently Asked Questions
What is the difference between maximum demand and connected load?
Connected load is the sum of all circuit breaker ratings. Maximum demand applies diversity factors to account for the fact that not all loads operate simultaneously — typically reducing the total by 60-80%.
Which standard should I use for maximum demand calculation?
Use AS/NZS 3000 for Australia/NZ, BS 7671 for UK, IEC 60364 for international projects, or NEC Article 220 for US projects. Each standard has different diversity factor tables.
How do diversity factors reduce maximum demand?
Diversity factors account for the statistical probability that not all loads peak simultaneously. For example, AS/NZS 3000 Table C1 applies 0.5 diversity to individual dwelling units in a 100+ unit apartment building.

Lead Electrical & Instrumentation Engineer
18+ years of experience in electrical engineering at large-scale mining operations. Specializing in power systems design, cable sizing, and protection coordination across BS 7671, IEC 60364, NEC, and AS/NZS standards.
Related Articles
How to Apply Diversity Factors in Maximum Demand Calculations (AS/NZS 3000)
Diversity factors are the difference between a 400A switchboard and a 1000A switchboard. Learn how to correctly apply AS/NZS 3000 Appendix C diversity to industrial, commercial, and residential loads.
Neutral Sizing: The Hidden Third Harmonic Problem Nobody Calculates
In balanced 3-phase systems, engineers assume neutral current is zero. With LED lighting and SMPS loads, 3rd harmonic currents ADD in the neutral — reaching 173% of phase current. Here's the calculation most designs miss.
Short Circuit Ratings: The Cable Nobody Checks (Until It Fails)
Most engineers size cables for ampacity and voltage drop. The adiabatic equation (k²S² ≥ I²t) is often forgotten. Here's a real scenario where a properly-sized 4mm² cable fails at 16kA — and how to check yours.