Skip to main content

Worked Example: Transformer Protection Coordination Study — The Sayano-Shushenskaya Dam Disaster

Complete transformer protection coordination study: fault current calculations per IEC 60909, protection device grading from transformer to final circuit, and how inadequate protection coordination contributed to the worst hydroelectric disaster in history.

IEC 6036422 min readUpdated February 24, 2026
Share:

The Incident: When Protection Fails to Coordinate

On 17 August 2009, a catastrophic failure at the Sayano-Shushenskaya hydroelectric dam in Siberia killed 75 workers and destroyed 9 of 10 turbine generators (6,400 MW total capacity). Turbine Unit 2 experienced a turbine cover blowout caused by metal fatigue from years of vibration, launching the 900-tonne rotor assembly through the turbine hall ceiling. The resulting flood destroyed the plant’s entire electrical infrastructure.

The investigation revealed that the plant’s protection systems should have detected abnormal vibrations and tripped the generator months before the catastrophic failure. But protection relay coordination between the generator, step-up transformer, and grid connection was misconfigured. Vibration-induced harmonic currents were not recognised as fault conditions because the protection was set only for fundamental-frequency overcurrent and earth fault — not for the harmonic distortion signature of a mechanically damaged generator.

While the Sayano-Shushenskaya disaster involved generator-class equipment far larger than most engineers will ever design, the protection coordination principle is identical at every voltage level. When a 1,000 kVA distribution transformer feeds an LV switchboard, the same discipline must ensure that a fault on an outgoing circuit trips the local MCCB — not the upstream transformer fuse. Getting this wrong means a localised fault blacks out the entire building instead of just the affected circuit.

Scenario: 1,000 kVA Transformer Protection Grading Study

Perform a protection coordination study for a 1,000 kVA distribution transformer feeding an LV switchboard with multiple outgoing circuits.

ParameterValue
Transformer1,000 kVA, 11 kV / 415 V, Dyn11
Impedance (uk%)5.0% nominal (±10% manufacturing tolerance per IEC 60076-1)
11 kV source fault level250 MVA
Transformer HV protection63 A BS 88 HRC fuses
LV main MCCB1,600 A frame, electronic trip unit (adjustable)
Outgoing MCCB400 A frame, thermal-magnetic
Final distribution board MCB32 A Type C
Primary standardIEC 60909-0:2016

Step 1: Calculate Transformer Rated Currents

Primary (11 kV) rated current:

In1 = S / (√3 × V1) = 1,000,000 / (√3 × 11,000) — (Eq. 1)

In1 = 52.5 A

Secondary (415 V) rated current:

In2 = S / (√3 × V2) = 1,000,000 / (√3 × 415) — (Eq. 2)

In2 = 1,391 A

Step 2: Calculate Source Impedance (Referred to LV Side)

The 11 kV source fault level is 250 MVA. The source impedance referred to the 415 V side:

Zsource = V2² / Ssource = 415² / 250,000,000 — (Eq. 3)

Zsource = 172,225 / 250,000,000 = 0.000689 Ω (0.689 mΩ)

This is the upstream network impedance as seen from the 415 V secondary bus. It is very small compared to the transformer impedance, meaning the transformer dominates the fault current calculation.

Step 3: Calculate Transformer Impedance (Three Scenarios)

The transformer’s impedance referred to the secondary (LV) side, per IEC 60909-0, Clause 6.3:

ZT = uk% × V2² / (100 × Sn) — (Eq. 4)

Crucially, IEC 60076-1 Clause 9.1 allows a manufacturing tolerance of ±10% on the declared impedance. We must calculate at all three values:

Scenariouk%ZT (Ω)
Nominal5.0%0.05 × 415² / 1,000,000 = 0.00862 Ω
Minimum (max fault current)4.5%0.045 × 415² / 1,000,000 = 0.00776 Ω
Maximum (min fault current)5.5%0.055 × 415² / 1,000,000 = 0.00948 Ω

Step 4: Calculate Prospective Fault Current at LV Bus

The total impedance is the sum of source and transformer impedance. The three-phase symmetrical short-circuit current per IEC 60909-0, Clause 4.2:

Ik” = c × Vn / (√3 × Ztotal) — (Eq. 5)

Where c = 1.0 (voltage factor for maximum current calculation per IEC 60909 Table 1, for LV systems).

ScenarioZtotal (mΩ)Ik” (kA)
Nominal (uk = 5.0%)8.62 + 0.69 = 9.31415 / (√3 × 0.00931) = 25.7 kA
Min impedance (uk = 4.5%)7.76 + 0.69 = 8.45415 / (√3 × 0.00845) = 28.4 kA
Max impedance (uk = 5.5%)9.48 + 0.69 = 10.17415 / (√3 × 0.01017) = 23.6 kA
The aha moment: The ±10% impedance tolerance produces a 22% spread in fault current: from 23.6 kA to 28.4 kA. An engineer who calculates only at the nominal 25.7 kA risks two failures: (1) switchgear rated at 25 kA could be exceeded if the transformer tests at 4.5% impedance (28.4 kA), and (2) protection discrimination at 23.6 kA may be different from discrimination at 28.4 kA. Both extremes must be checked.

Step 5: Select Switchgear Fault Rating

The LV switchboard and all protective devices must be rated for the maximum prospective fault current, which occurs at minimum transformer impedance:

Switchgear fault rating ≥ 28.4 kA

Standard fault ratings for LV switchgear: 10, 16, 25, 36, 50, 65 kA.

Selected: 36 kA rated switchboard (next standard rating above 28.4 kA).

Common error: An engineer calculating at nominal impedance (25.7 kA) would select a 25 kA rated switchboard. If the transformer tests at 4.5% impedance, the prospective fault current of 28.4 kA exceeds the switchgear rating by 13.6%. This is a latent safety hazard — the switchgear may fail catastrophically during a fault, with potential for arc flash and explosion.

Step 6: Protection Grading — Time-Current Coordination

Protection coordination requires that for any fault current, the device closest to the fault trips first (discrimination). We check four levels of protection:

Level 1: Transformer HV fuse (63 A BS 88)

The HV fuse must be the last device to operate. At 28.4 kA on the LV side, the equivalent HV current is:

IHV-fault = Ik” × V2 / V1 = 28,400 × 415 / 11,000 = 1,071 A (referred to HV side) — (Eq. 6)

BS 88 63 A fuse operating time at 1,071 A: approximately 0.01 s (well within the fuse’s fast-acting region).

Level 2: LV main MCCB (1,600 A, electronic trip)

Settings: Long-time pickup = 1.0 × In (1,600 A), long-time delay = 12 s. Short-time pickup = 3 × In (4,800 A), short-time delay = 0.2 s. Instantaneous = 12 × In (19,200 A).

At 28.4 kA: instantaneous trip in < 0.02 s.

Level 3: Outgoing MCCB (400 A, thermal-magnetic)

Magnetic trip at 10 × In = 4,000 A. At 28.4 kA: instantaneous trip in < 0.01 s.

Level 4: Final MCB (32 A Type C)

Type C magnetic trip at 5–10 × In = 160–320 A. At any fault exceeding 320 A: instantaneous trip in < 0.01 s.

Step 7: Discrimination Check at Both Impedance Extremes

The critical discrimination check is between the LV main MCCB and the outgoing MCCBs. For discrimination (selectivity), the upstream device must have a longer operating time than the downstream device at every fault current level.

At maximum fault current (uk = 4.5%, Ik” = 28.4 kA):

DeviceOperating TimeDiscriminates?
Level 4: 32 A MCB< 0.01 s (instantaneous)✓ Fastest
Level 3: 400 A MCCB< 0.01 s (instantaneous)▵ Same as Level 4
Level 2: 1,600 A MCCB< 0.02 s (instantaneous above 19.2 kA)✗ Trips before Level 3 clears
Level 1: HV fuse0.01 s✗ Insufficient margin
Discrimination failure! At 28.4 kA, ALL four devices attempt to trip simultaneously (all in their instantaneous region). The 32 A MCB may clear fastest (< 5 ms for fault on final circuit), but a fault on the 400 A outgoing MCCB feeder will cause the 1,600 A main MCCB to trip as well — blacking out the entire switchboard instead of just the faulted outgoing circuit.

At minimum fault current (uk = 5.5%, Ik” = 23.6 kA):

The situation is slightly better because 23.6 kA exceeds the main MCCB instantaneous pickup (19.2 kA), so the main MCCB still trips instantaneously. Discrimination still fails.

For fault currents below the main MCCB instantaneous pickup (< 19.2 kA):

The main MCCB operates on its short-time delay (0.2 s) while the outgoing MCCB operates instantaneously (< 0.01 s). Discrimination margin: 0.19 s. ✓ Discriminates for faults below 19.2 kA.

Step 8: Engineering Solutions for Discrimination

To achieve full discrimination up to the maximum prospective fault current:

Option A: Increase the main MCCB instantaneous pickup (recommended):

Set the main MCCB instantaneous trip to its maximum: 20 × In = 32,000 A. Since the maximum fault current is 28.4 kA, the main MCCB will never enter its instantaneous region for transformer-fed faults. It will operate on the short-time delay (0.2 s) for ALL faults up to 28.4 kA, providing 0.19 s discrimination margin over the outgoing MCCBs.

Main MCCB settings (revised): Instantaneous = 20 × In (32,000 A) — (Eq. 7)

Option B: Use current-limiting outgoing MCCBs:

Current-limiting MCCBs interrupt the fault within the first half-cycle (5 ms at 50 Hz), limiting the let-through energy (I²t). If the outgoing MCCB’s let-through I²t is below the main MCCB’s non-trip I²t threshold, energy-based discrimination is achieved even when both devices operate in the instantaneous region.

Option C: Use zone-selective interlocking (ZSI):

A restraint signal from downstream MCCBs to the upstream MCCB prevents the upstream device from tripping in its instantaneous region when a downstream device detects the fault. This provides full discrimination at any fault level but requires compatible electronic trip units and interconnecting wiring.

Result Summary

CheckNominal (5.0%)Min Z (4.5%)Max Z (5.5%)Status
Fault current at LV bus25.7 kA28.4 kA23.6 kA22% spread
Switchgear rating (36 kA)✓ PASS
Discrimination (original settings)✗ FAIL
Discrimination (revised Imag = 20×)✓ PASS

Result: The ±10% impedance tolerance on the 1,000 kVA transformer produces a fault current range of 23.6–28.4 kA. Switchgear must be rated for the maximum (28.4 kA, requiring 36 kA rated equipment). Protection discrimination initially fails because the main MCCB’s instantaneous trip at 19.2 kA overlaps with the fault level range. Adjusting the instantaneous pickup to 20× In (32 kA) resolves the discrimination issue while maintaining short-time delay protection for all transformer-fed faults.

What Would Have Prevented This?

The Sayano-Shushenskaya disaster was caused by metal fatigue from vibration, not protection coordination failure per se. However, the investigation found that better-configured protection systems could have detected the deteriorating condition and tripped the generator before catastrophic failure:

  • Always check discrimination at both impedance tolerance extremes — a protection grading study at nominal impedance only is incomplete and potentially dangerous
  • Rate switchgear for maximum prospective fault current — use the minimum impedance tolerance (uk − 10%) when calculating the fault current that switchgear must withstand
  • Use the maximum impedance tolerance (uk + 10%) when checking earth fault protection — higher impedance means lower fault current, which may be insufficient to trip the protective device within the required time
  • Implement time-graded discrimination for all cascaded protection devices — the upstream device must have a deliberate time delay (typically 0.2–0.4 s) to allow the downstream device to clear first
  • Document the protection study — a time-current grading chart showing all devices should be produced for every new installation and updated whenever protection settings are changed

Try the Short Circuit Calculator

Put this methodology into practice. Calculate results with full standard clause references — free, no sign-up required.

Or embed this calculator on your site
Calculate Short Circuit

Frequently Asked Questions

Transformer impedance is determined by the physical geometry of the windings — conductor spacing, number of turns, and core dimensions. Manufacturing variations in winding tension, insulation thickness, and core assembly mean the actual impedance may differ from the design value. IEC 60076-1 Clause 9.1 permits ±10% on the declared impedance for transformers where impedance is not guaranteed. For transformers with a guaranteed impedance (specified as a tested value), the tolerance is reduced to ±7.5%.
ZSI is a communication system between cascaded protective devices. When a fault occurs, all devices in the fault path detect it. The device closest to the fault sends a restraint signal to upstream devices, telling them 'I've got this — don't trip yet.' The upstream device adds a deliberate time delay (typically 0.1-0.2 s) to allow the downstream device to clear the fault first. If the downstream device fails to clear, the upstream device trips as backup. ZSI provides full discrimination at any fault level without requiring the main MCCB instantaneous pickup to be set above the maximum fault current.
Both. Use maximum fault current (minimum impedance tolerance) for: switchgear rating, cable thermal withstand, and checking that upstream devices do not trip before downstream devices. Use minimum fault current (maximum impedance tolerance) for: verifying that protective devices operate fast enough for earth fault disconnection times (BS 7671 Regulation 411.3.2), and confirming that MCBs reach their magnetic trip threshold for instantaneous disconnection. A complete protection study requires calculations at both extremes.

Related Resources